Reducing Project Delays from 65% to 15% with Critical Chain
Source: Dev.to

65% of IT projects are delayed.
People say “couldn’t help it.”
One company reduced the delay rate from 65% to 15% using the Critical Chain (CCPM) methodology.
Problems with Traditional Approach
The traditional approach adds individual buffers to every task:
Task A (5 days + 3 day buffer) → Task B (3 days + 2 day buffer) → Task C (4 days + 3 day buffer)
Total: 20 days
Why is this a problem?
Parkinson’s Law states that “work expands to fill the time available.” Giving a 5‑day task a 3‑day buffer means the task will likely take the full 8 days. Even if finished early, the team doesn’t move to the next task because “we have time anyway,” leading to slower work.
CCPM Innovation
CCPM removes individual buffers and places a single integrated buffer at the end of the project:
Task A (5 days) → Task B (3 days) → Task C (4 days) → [Project Buffer 4 days]
Total: 16 days (20% shorter!)
The concept is simple, but the effect is powerful.
Implementation Method
def calculate_ccpm_schedule(tasks):
"""Calculate CCPM schedule"""
# Aggressive estimates (50% probability)
aggressive_estimates = []
for task in tasks:
# Traditional: Includes safety margin (90% probability)
conservative = task["estimate"]
# CCPM: 50% probability of completion
aggressive = conservative * 0.6
aggressive_estimates.append({
"name": task["name"],
"duration": aggressive
})
# Project buffer (50% of total)
total_duration = sum(t["duration"] for t in aggressive_estimates)
project_buffer = total_duration * 0.5
return {
"tasks": aggressive_estimates,
"buffer": project_buffer,
"total": total_duration + project_buffer
}
A 40‑day project becomes 30 days.
Buffer Management is Key
Daily monitoring of buffer consumption is essential.
function checkBufferStatus(projectProgress, bufferConsumed) {
const ratio = bufferConsumed / projectProgress;
if (ratio progress * 1.5:
self.alert("🔴 Excessive buffer consumption!")
return [
"Root cause analysis",
"Additional resource input",
"Review scope adjustment"
]
CCPM Success Factors
- Management Support – Requires a mindset shift away from blaming individual task delays.
- Accurate Measurement – Daily tracking of buffer consumption and task completion rates.
- Culture Change – Encourage immediate transition to the next task when one finishes early.
Expected Effects
Applying CCPM properly yields:
- Project duration: ‑25 %
- Delay rate: 65 % → 15 %
- Buffer efficiency: 40 % → 85 %
- Team stress: Greatly reduced
- Prediction accuracy: 2× improvement
Conclusion
CCPM looks simple but is powerful. The key is removing individual buffers, consolidating them into a project‑level buffer, and monitoring consumption rigorously. “Impossible schedules” become “possible schedules.”
Try it in your next project.
Want to reduce project delays? Check out Plexo.